Goodeng Machine GMD80s Down-the-Hole Surface Drilling Rig Russian Susuman Gold Project
2026-04-16
Project details:
1. Geological conditions: gravel + sandstone + frozen soil .
2.Construction: Two shifts, 24-hour work system. Single shift 12 hours.
Fastest drilling reached 126 holes (756 meters), approximately 1500 meters per day.
Average daily efficiency: approximately 1000-1200 meters.
3. Temperature: From October to May, the temperature is consistently between -50°C and -10°C.
This construction operation was conducted in the temperature range of -35°C to -10°C.
4. Equipment maintenance: Daily maintenance once per shift. Initial maintenance every 250 hours, subsequent maintenance every 500 hours, and so on.

CONTACT:
Evangelin
Whatsapp:+86 13601615181
Mobile: +86 18352028025
Email: linlaixian@goodeng.com.cn

