Goodeng Machine G130 has finished HDD Projects in Switzerland
2026-05-12
Project details:
1. Geological conditions: gravel + sandstone + frozen soil ย .
2.Construction: Two shifts, 24-hour work system. Single shift 12 hours.
Fastest drilling reached 126 holes (756 meters), approximately 1500 meters per day.
Average daily efficiency: approximately 1000-1200 meters.
3. Temperature: From October to May, the temperature is consistently between -50ยฐC and -10ยฐC.
This construction operation was conducted in the temperature range of -35ยฐC to -10ยฐC.
4. Equipment maintenance: Daily maintenance once per shift. Initial maintenance every 250 hours, subsequent maintenance every 500 hours, and so on.